Bid preparation schedule
Week | Tasks | Milestones |
---|---|---|
16-22 March | Discussion on general objectives, approach, consortium, WPs, leaders, etc. Whole consortium Meeting | A first draft on all documents. First guess of in-kind and person-month |
23-29 March | Iteration of WPs drafts. Release of a second version of common parts (project office).Discussion of budget, milestones, deliverables, etc. | Almost consolidated WP descriptions, milestones, deliverables, budget. Administrative information almost complete |
30- 6 | First version of full proposals to discuss and final corrections | All administrative information checked Full proposal ready. Final days to complete with letters of support if necessary |
6- 8 April | Submission process | Better starting on 6th April. |