Bid preparation schedule

Week Tasks Milestones
16-22 March
Discussion on general objectives, approach, consortium, WPs, leaders, etc.

Whole consortium Meeting
A first draft on all documents. First guess of in-kind and person-month
23-29 March Iteration of WPs drafts. Release of a second version of common parts (project office).Discussion of budget, milestones, deliverables, etc. Almost consolidated WP descriptions, milestones, deliverables, budget. Administrative information almost complete
30- 6 First version of full proposals to discuss and final corrections
All administrative information checked

Full proposal ready. Final days to complete with letters of support if necessary
6- 8 April Submission process Better starting on 6th April.