management:schedule
~~COMPLEX_TABLES~~
Próximos eventos y fechas de entrega
1 Junio 10h | Teleconferencia | Reunión TAS, IAA, Phillippe respecto los diseños propuestos del IAA-TAS. Para entregar a SRR | Isidro, Pedro Rodriguez y Raúl. Juanma, Bea, Julio, Rosario, JC Phillipe. | PLATO MEU Design options Technical note_ Issue1_1 minutas: PLATO-UGRIAA-TAS-LESIA-002MoM_06012015.docx | |
PM#4 | 15July (13h)-17 July (16h) | DLR, Berlin - From Wednesday, 15.07.2015 13:00 until Thursday 16.07.2015 13:00 we will organize Splinters to prepare the PM meeting with ESA - From Thursday, 16.07.2015 14:00 until Friday 17.07.2015 ~16:00 will be the official PM#4, together with representatives from ESA, CNES and DLR Agency. |
Julio 2015 | Actualizar los WPDs para B2/C/D. Ver PLATO-MIMG_MS_24-CNES | |||||||||
31Julio | primera interacion con los documentos de SRR | |||||||||
7Septiembre | entrega DEFINITIVA de documentos SRR The SRR Data Package consists of Updated PDCR Document Incorporate all resulting AIs, Board Report issues, recommendations, RID panel dispositions Additional Documents, not requested or available for the PCDR All Docs mentioned in the DRL [AD7] have to be provided Please check: PLATO Payload Document Requirements List (P/L DRL) Tailored Document lists circulated for the PDCR | |||||||||
18 Nov | Delivery of SRR Data Package to ESA SRR colocation | |||||||||
KO | 23 Feb 2016 | Munich | Kick-Off Phase B2 | |||||||
PM#5 | Feb 2016 | Munich | ESA,P/L Consortium | |||||||